Building Permit Authority

Billings Building Permit Office

City of Billings Building Division

Active Last verified: 2026-10-04 Montana
City / County
Billings
Jurisdiction
City of Billings
Address
316 N 26th Street, 5th Floor, Billings, Montana, 59101
Google Maps Permit office location

Billings is a certified local building-code jurisdiction, but the City Building Division’s authority generally stops at the Billings city limits. Projects inside the city use the City of Billings permitting system; construction outside the city may fall under the Montana Building Codes Program while still requiring separate Yellowstone County planning, health, floodplain, road or other local approvals.

Jurisdiction

City Limits Determine the Building Permit Authority

Inside Billings

City Building Division

The City of Billings Building Division administers building permits within the city limits. Montana lists Billings as a certified local building-code jurisdiction, and the City also administers electrical, plumbing and mechanical permitting within its certified scope.

Outside Billings

State and County Requirements May Apply

The City does not issue building, plumbing, mechanical or electrical permits for property outside the city limits. The Montana Building Codes Program handles state-regulated construction in areas outside certified local jurisdictions. City/County Planning, Yellowstone County agencies and RiverStone Health can still have authority over zoning, septic, floodplain, access or other site matters.

Do not use a Billings mailing address to determine jurisdiction

A property can have a Billings postal address without being inside the municipal boundary. Confirm whether the parcel is inside Billings before selecting the building-permit authority.

Online Filing

Billings Building Permits Are Submitted Through CityView

The Building Division requires online submission of permits. The CityView Portal is used to create building-permit applications, upload submittals, estimate certain fees, search applications and follow permit status. Planning and Engineering applications are also available through the same portal under their respective departments.

1

Confirm the parcel and required approvals

Check the city boundary and zoning before preparing the building application. A project that needs a zoning action, master site plan, variance or other planning approval may have additional review before the building permit can be completed.

2

Create the CityView application

Register for the CityView Portal, select the appropriate Building Department application and enter the project information requested by the City.

3

Upload the plans and project documents

Billings accepts plans electronically, so only one electronic plan set is required. The documents depend on the work being proposed and may include site, architectural, structural, plumbing, mechanical and electrical information.

4

Respond to review comments

The permit can pass through several City reviews. Applicants can follow the application in CityView and submit requested revisions or additional documents. The City sends an email notification after the reviewing departments and divisions have completed their reviews.

5

Request required inspections

Building inspections can be requested through the Building Division by email at inspections@billingsmt.gov or by calling 406-657-8270. Inspection approval is separate from simply having a permit issued.

Plans

What Billings Reviews in a Building Submittal

The City’s published permit material calls for plans that show enough information to review the project for applicable codes, laws and ordinances. Depending on the project, review can cover the site, structure, architecture, plumbing, mechanical work and electrical work.

  • Project address, owner and contractor information
  • Description and proposed use of the work
  • Project valuation
  • Site information and applicable site plans
  • Architectural and structural drawings when required
  • Mechanical, plumbing and electrical information appropriate to the project
  • Additional Planning, Engineering or Fire documentation when the project requires those reviews

Commercial plans that require professional design are identified by the City as needing a Montana-licensed architect or engineer. For single-family residential projects, the City states that some plumbing and electrical detail can be omitted when allowed, provided required equipment locations and other necessary information are shown.

Incomplete plans can delay the review cycle

Billings reviews projects by type and generally in the order received. Detailed plans and complete supporting documents reduce the need for correction cycles.

Review Times

Published Initial Plan Review Timeframes

For a complete submittal with preliminary land-use issues already addressed, the Building Division currently publishes the following initial review ranges:

Residential

Single-Family and Duplex

4–7 business days for the initial review.

Commercial

Minor Projects

2–4 weeks for the initial review.

Commercial

Major Projects

3–6 weeks for the initial review.

Those ranges apply after a complete plan has been submitted and issues such as variances, special reviews or subdivision matters have been addressed. Corrections, agency coordination or project-specific conditions can extend the overall permit process.

Planning

Zoning Review Is Separate from Building-Code Review

The City/County Planning Division administers zoning for the City of Billings and applicable Yellowstone County zoning areas. Planning applications can include zoning compliance, master site plans, fence and sign permits, temporary uses, zoning clarifications, variances, special reviews and zone changes.

Billings implemented its Billings 2045 Zoning Code update effective July 1, 2026. Setbacks, allowed uses and other land-use requirements therefore need to be checked against the current zoning rules rather than older project standards. Planning applications are submitted through CityView.

A building permit does not substitute for a required planning approval. Some projects must clear Planning, Engineering, Fire or another reviewing division as part of the City’s development process.

Permit Scope

Work That Commonly Reaches the Building Division

The City identifies roofing, siding, decks and parking-lot construction among work that can require a building permit. Separate permits can also be required when electrical, plumbing, mechanical or other regulated work is performed.

Billings also publishes examples of work that does not require a building permit, including painting, wallpaper and similar finish work, and detached sheds not exceeding 200 square feet. Sidewalks or driveways located entirely on private property may also be exempt from the building permit when they do not support a structure. Other City permits can still apply even when a building permit is not required.

Public right-of-way work follows different rules

Construction affecting a public right-of-way can require an Engineering permit and may require a licensed and bonded contractor. A private-property building permit should not be treated as authorization to perform work in the street or public right-of-way.

Fees

Billings Changed Its Permit Fee Schedule in 2026

Resolution 26-11315, adopted February 23, 2026 and effective upon passage, establishes the current City schedule for building, electrical, plumbing, mechanical and fire-system permit fees.

Commercial and residential building-permit fees are valuation-based. The resolution directs the City to use the higher of the total bid-price value or the applicable valuation calculated from the most recent International Code Council valuation table. For commercial projects, the resolution sets the plan-review fee at 60% of the building permit fee.

Electrical, plumbing, mechanical and fire-system work have their own schedules. The final amount can therefore include more than the base building-permit charge when a project contains multiple regulated systems.

Inspections

Building and Fire Inspections

Required building inspections are scheduled through the Building Division by email or phone. Work should remain accessible for inspection and should not be covered before the required inspection has been completed.

Commercial buildings, additions and remodels reviewed by the Billings Fire Prevention Bureau can also require a Fire final before certificate-of-occupancy approval. The Fire Department directs applicants to schedule those final construction inspections through the Building Division with at least 24 hours’ notice. Projects with fire alarms, sprinklers or other fire-protection systems may require additional acceptance testing.

Code Editions

Billings Is in a State Code-Cycle Transition

The City’s current adopted-codes page continues to list the 2021 International Building, Residential, Existing Building, Mechanical, Fuel Gas and Energy Conservation codes, the 2021 Uniform Plumbing Code and the 2020 National Electrical Code under the City’s 2022 administrative adoption.

Montana, however, moved to its 2024 state code cycle on September 26, 2026, including the 2024 IBC, IRC, IEBC, energy, plumbing and mechanical codes and the 2023 National Electrical Code. Montana requires certified local programs to conform their adopted codes following state changes. Projects being designed or submitted during this transition should confirm the applicable code edition directly with the Billings Building Division.

Outside City Limits

Construction in Yellowstone County Is Not Automatically a City Permit

For construction outside the Billings municipal boundary, the Montana Building Codes Program may issue state building, electrical, plumbing and mechanical permits where state law requires them. State building-permit exemptions also exist for certain property types, including some residential buildings with fewer than five dwelling units, farm and ranch buildings and qualifying private garages or storage structures.

A state building-permit exemption does not remove separate land-use requirements. Property outside Billings can still be subject to Yellowstone County zoning, subdivision rules, floodplain requirements, wastewater or septic review, road-access requirements and other local regulations.

Official Resources

Billings Permit and Planning Links

Building Division

City of Billings Building Division

City building-permit information, permit guidance and Building Division contacts.

Open Building Division

Permit Portal

CityView Portal

Apply for permits, upload documents, search applications and check permit status.

Open CityView

Forms

Building Applications and Forms

Building applications, residential plan material, inspection information and commercial forms.

View Building Forms

Planning

Planning Permits and Applications

Zoning compliance, master site plans, signs, fences, variances and other planning applications.

View Planning Applications

Fees

2026 Permit Fee Resolution

Resolution 26-11315 contains the current City schedules for building and associated trade-permit fees.

View 2026 Fee Resolution

State Jurisdiction

Montana Building Codes Program

State permit applications and current code information for projects under Montana jurisdiction outside certified local programs.

Open Montana Building Codes